Closed
Damage to footway during SU works
Reported in the Pothole / Failed Reinstatement category anonymously at 17:16, Wed 8 May 2019
Sent to Northamptonshire Highways 4 minutes later. ref: 1624115.
Work on going to install gas main appears to have destroyed footway. Trust contractors will be required to reinstate it as part of their works (?)
Updates
-
Thank you for reporting a fault on the highway. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 17:20, Wed 8 May 2019
-
I see that the contractors were today soiling and seeding over the area where a large length of the footway used to be. Have you carried out an inspection/spoken to the contractor about reinstatement? Or are we niow expected to walk in the carriageway?
Posted anonymously at 19:19, Tue 21 May 2019
-
Thank you for your enquiry This is correct one work is completed I will inspect works and all remedial work will be agreed this then will have 2 Year guarantee period
Posted by Northamptonshire Highways at 14:43, Sun 9 June 2019
-
State changed to: Closed
Updated by Northamptonshire Highways at 07:15, Wed 28 August 2019
This report is now closed to updates from the public. You can make a new report in the same location.