Drain is collapsing.
Reported in the Blocked/Damaged category anonymously at 16:27, Fri 9 August 2019
Sent to Northamptonshire Highways 4 minutes later. ref: 1726459.
The drain has started to collapse inwards due to construction traffic using the road. Drain is near to the "No Construction Traffic" sign on the left going up the road.
Updates
-
Thank you for reporting a fault on the highway. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 16:31, Fri 9 August 2019
-
The collapsing drain is down the road from the "No Construction" sign and is opposite the gate to the building site.
State changed to: Open
Posted anonymously at 14:55, Sat 10 August 2019
-
Works order rasied and will be undertaken within the next 6 months thank you
State changed to: Action scheduled
Posted by Northamptonshire Highways at 13:35, Mon 12 August 2019
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 16:05, Tue 22 October 2019
This report is now closed to updates from the public. You can make a new report in the same location.