Fixed
Large 2-3 level hole is by the new development - Quarry Fields
Reported in the Potholes / Highway Condition category anonymously at 08:12, Fri 30 August 2019
Sent to Northamptonshire Highways 3 minutes later. ref: 1749386.
Pothole has been there for more than 2 months and now that most of the heavy traffic for Quarry Fields has stopped it can and should be repaired. The whole of Finedon Road is very poorly maintained and quite frankly needs to be completely recovered exactly as the section of road down by Bosworths was done. Why it was stopped short of Hillcrest Ave is puzzling.
Updates
-
Thank you for reporting a fault on the highway. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 08:15, Fri 30 August 2019
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:08, Wed 4 September 2019
-
18th September and at this point in time the repairs have not been done.. any update on when they will be completed?
Posted anonymously at 10:13, Wed 18 September 2019
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 12:20, Tue 24 September 2019
This report is now closed to updates from the public. You can make a new report in the same location.