Closed
Missing Panels
Reported in the Slabs - Uneven / Damaged / Cracked category anonymously at 12:22, Mon 3 February 2020
Sent to Northamptonshire Highways 12 minutes later. ref: 1976102.
Hello, One panel is missing from the bridge parapet at Mill Lane. This was previously reported in April 2019, could you please give us an update on when a permanent repair is planned? This is posing a safety hazard to the railway underneath the bridge. Thank you
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 12:34, Mon 3 February 2020
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:16, Tue 4 February 2020
-
Thank you for contacting Northamptonshire Highways. We can confirm that Northamptonshire Highways regularly inspects the panels and we are in the process of developing a scheme that will not only repair the panels but also incorporate a PTSI inspection / PI and concrete testing. The last inspection photos show no change in the panel condition. We anticipate works to be completed by end 2021.
Posted by Northamptonshire Highways at 14:24, Tue 4 February 2020
-
As part of a system review we have noted that this report has remained open and we have now closed the report to future updates. If for any reason you believe that the report should not have been closed please raise a new report. Please provide the old reference number and an explanation as to why you believe the report should not have been closed so we can investigate this further.
State changed to: Closed
Posted by Northamptonshire Highways at 15:45, Wed 30 March 2022
This report is now closed to updates from the public. You can make a new report in the same location.