Fixed
Pot hole NOT fixed.
Reported in the Potholes / Highway Condition category anonymously at 15:06, Thu 13 August 2020
Sent to Northamptonshire Highways less than a minute later. ref: 2243942.
Hi, Ive received an email notification saying this has been fixed (ref 2234187) . Clearly it hasn't. Vehicles are having damage to them and stock is arriving collapsed on pallets having to drive through this. Can you please raise and support. Many thanks
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 15:06, Thu 13 August 2020
-
Thank you for your enquiry. A safety repair has been carried out. permanent repairs are to be undertaken week commencing on the 5th of october 2020 works.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 15:30, Wed 2 September 2020
-
We are a neighbouring factory, this damage to the road is a hazard and risk for our employees, whether they are driving, walking or cycling. It's not a pothole, the damage is over a wide area. You have to drive over with extreme caution, Can this be fixed as a matter of priority, before there are claims for damage to cars and/or personal injury.
Posted anonymously at 09:06, Wed 21 October 2020
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 10:22, Wed 21 October 2020
-
Thank you for your enquiry. A safety repair has been carried out. permanent repairs are to be undertaken week commencing on the 5th of october 2020 works. update 22-10-20 Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 7 days.
State changed to: In progress
Posted by Northamptonshire Highways at 15:27, Thu 22 October 2020
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 15:28, Thu 22 October 2020
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 06:55, Wed 28 October 2020
This report is now closed to updates from the public. You can make a new report in the same location.