Back to all reports

Numerous potholes

Reported in the Potholes / Highway Condition category by Derek M Everett at 13:59, Fri 14 August 2020

Sent to Northamptonshire Highways less than a minute later. ref: 2245456.

Potholes are getting worse

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 13:59, Fri 14 August 2020

  • Thank you for your enquiry. A works order has been raised and will be completed within 6 months to repair the potholes.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 21:16, Tue 18 August 2020

  • Potholes are getting much worse and vehicles are going into the centre of the road to avoid heading towards Cosgrove - particularly on the first two bridges after the Navigation Pub. There are pot holes in the centre of the road as well. Concern there will be accidents and concern for vehicle damage. Needs escalating urgently due to road condition. Whole road really needs resurfacing as patch work has been insufficient.

    Posted anonymously at 14:42, Thu 12 November 2020

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 14:43, Thu 12 November 2020

  • Thank you for your enquiry. Larger potholes have been repaired to make safe and a works order has already been raised and will be completed within 3 months to repair carriageway potholes that meet ncc investigatory levels.

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:52, Mon 16 November 2020

  • The pot holes in the centre of the road situated after the Navigation Inn / canal bridge on the section of road leading towards the River Tove Bridge Castlethorpe direction are now extremely severe and very deep . Cars will be damaged and high risk of a road traffic accident . The edges of this road are also experiencing heavy subsidence and loss of road material . Originally reported on 12/11/2020 , updated above states these have been addressed , no work has been carried out at all

    Posted anonymously at 13:06, Mon 14 December 2020

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 13:07, Mon 14 December 2020

  • Thank you for your enquiry. A works order has already been raised and will be completed within 2 months to repair carriageway potholes. However works have been scheduled for 17.12.20 (weather permitting) to repair the carriageway potholes and will try to complete in one day.

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:04, Wed 16 December 2020

  • Thank you for reporting a fault on the highway, the highways team have now resolved the issue.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 13:40, Thursday 7 January 2021

This report is now closed to updates. You can make a new report in the same location.