Fixed
Serious deep potholes outside 22a 22b and 22c pilgrims lane due to heavy rain becoming dangerous for vehicles
Reported in the Potholes / Highway Condition category anonymously at 09:24, Tue 25 August 2020
Sent to Northamptonshire Highways less than a minute later. ref: 2262008.
Potholes here for months worsening due to heavy rain
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 09:24, Tue 25 August 2020
-
Thank you for your enquiry. A works order has been raised and will be completed within 6 months to repair the potholes.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 09:15, Thu 27 August 2020
-
The issue has also been raised by me with the county councillor responsible he informs me he is pursuing whatever that means
Posted anonymously at 14:29, Tue 22 September 2020
Still open, via questionnaire -
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 14:30, Tue 22 September 2020
-
Thank you for your enquiry. A works order has been raised and will be completed within 6 months to repair the potholes. I can confirm there will be a resurfacing scheme to be carried out on pilgrims lane this financial year.
State changed to: In progress
Posted by Northamptonshire Highways at 11:59, Thu 24 September 2020
-
No progress so far potholes are worse with the rain we had
Posted anonymously at 15:50, Tue 20 October 2020
Still open, via questionnaire -
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 15:51, Tue 20 October 2020
-
Thank you for your enquiry. A works order has already been raised and will be completed within 4 months to repair the potholes. I can confirm there will be a resurfacing scheme to be carried out on pilgrims lane which is scheduled for 11.1.21.
State changed to: In progress
Posted by Northamptonshire Highways at 10:55, Fri 23 October 2020
-
The local councillor advised me work will take placein january
Posted anonymously at 19:36, Tue 17 November 2020
Still open, via questionnaire -
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 19:37, Tue 17 November 2020
-
State changed to: In progress
Updated by Northamptonshire Highways at 11:12, Thu 19 November 2020
-
Still open, via questionnaire, 05:19, Wed 16 December 2020
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 07:15, Thu 7 January 2021
This report is now closed to updates from the public. You can make a new report in the same location.