In progress
Drains are blocked in the cul-de-sac of Bath Lane
Reported in the Blocked/Damaged category anonymously at 10:42, Thu 27 August 2020
Sent to Northamptonshire Highways less than a minute later. ref: 2265948.
All the drains are blocked in the cul-de-sac of Bath Lane which are now causing issues with flooding in the premises of Wicksteed Leisure of Digby Street (factory backs on to Bath Lane)
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 10:43, Thu 27 August 2020
-
Thank you for your enquiry, site visited. works have been instructed and will be undertaken within 24 hours.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:28, Fri 28 August 2020
-
Last update, 28/8/2020, advised that works had been instructed and would be undertaken within 24 hours. Having just checked the drains, 11/9/2020, work appears not to have been undertaken as the drains are still blocked
Posted anonymously at 10:33, Fri 11 September 2020
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 10:33, Fri 11 September 2020
-
Thank you for your enquiry, site visited. works have been instructed and will be undertaken within 24 hours.
State changed to: In progress
Posted by Northamptonshire Highways at 13:15, Wed 23 September 2020
Provide an update