Fixed
Road surface now breaking up at an increasing rate!
Reported via iOS in the Potholes / Highway Condition category by Philip Parris - Pattishall Parish Councillor at 07:06, Mon 31 August 2020
Sent to Northamptonshire Highways less than a minute later. ref: 2271129.
Problem reported nearly 6 months ago! When is this road repair scheduled to be completed ?
Updates
-
The repair was promised within 6 months. All that has happened to date is yellow painted lines indicating the repair area!
Posted by Cllr Phil Parris - Pattishall Parish Council at 08:20, Mon 31 August 2020
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 08:20, Mon 31 August 2020
-
Is this repair ever going to be carried out?
State changed to: Investigating
Posted by Cllr Phil Parris - Pattishall Parish Councillor at 06:30, Tue 15 September 2020
-
Problem fixed - thank you
State changed to: Fixed
Posted by Cllr Phil Parris - Pattishall Parish Councillor at 08:01, Mon 28 September 2020
This report is now closed to updates from the public. You can make a new report in the same location.