Closed
Extensive road damage due to flooding
Reported via desktop in the Potholes / Highway Condition category anonymously at 13:53, Wed 3 February 2021
Sent to Northamptonshire Highways less than a minute later. ref: 2521899.
Mulitple deep potholes along this part of the road with debris being deposited on side of road
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 13:54, Wed 3 February 2021
-
Thank you for your enquiry, Site visited and works have been completed.
State changed to: In progress
Posted by Northamptonshire Highways at 08:33, Mon 15 February 2021
-
Passed this area this morning 15/2/21 and noted still a large number of flooded potholes with debris along side that have not been repaired.
Posted anonymously at 09:34, Mon 15 February 2021
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 09:35, Mon 15 February 2021
-
Thank you for your enquiry, Site visited and works have been completed Thank you for your enquiry,defects that meet NCC investigatory levels have been repaired, Area has been forwarded to the resurfacing programme, unfortunately we cannot give a date at this time, will continue to monitor through highway safety inspections.
State changed to: In progress
Posted by Northamptonshire Highways at 12:57, Wed 17 February 2021
-
As part of a system review we have noted that this report has remained open and we have now closed the report to future updates.
If for any reason you believe that the report should not have been closed please raise a new report.
Please provide the old reference number and an explanation as to why you believe the report should not have been closed so we can investigate this further.
State changed to: Closed
Posted by Northamptonshire Highways at 13:54, Tuesday 21 March 2023
This report is now closed to updates. You can make a new report in the same location.