Fixed
Pot holes
Reported via desktop in the Potholes / Highway Condition category anonymously at 19:39, Wed 24 March 2021
Sent to Northamptonshire Highways less than a minute later. ref: 2631760.
There are several pot holes starting from top of chestnut avenue to the bottom end
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 19:40, Wed 24 March 2021
-
State changed to: In progress
Updated by Northamptonshire Highways at 09:59, Fri 26 March 2021
-
Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so.
Posted by Northamptonshire Highways at 09:59, Fri 26 March 2021
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:01, Fri 26 March 2021
-
Still open, via questionnaire, 20:36, Wed 21 April 2021
-
Still open, via questionnaire, 21:19, Wed 19 May 2021
-
Potholes have worsened, Where the road is torn up it has left debris which has become dangerous
Posted anonymously at 11:43, Fri 28 May 2021
-
Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so. Update 2.6.21. Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 3 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so.
State changed to: In progress
Posted by Northamptonshire Highways at 09:54, Wed 2 June 2021
-
Potholes have worsened, Where the road is torn up it has left debris which has become dangerous
State changed to: Action scheduled
Posted anonymously at 18:10, Wed 16 June 2021
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 18:10, Wed 16 June 2021
-
Still open, via questionnaire, 06:13, Thu 17 June 2021
-
Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so. Update 2.6.21. Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 3 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so. Update 21.6.21. Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 18 days.
State changed to: In progress
Posted by Northamptonshire Highways at 10:22, Mon 21 June 2021
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 08:20, Tue 6 July 2021
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 11:35, Wed 14 July 2021
This report is now closed to updates from the public. You can make a new report in the same location.