Back to all reports

Previously Reported

Reported via iOS in the Potholes / Highway Condition category anonymously at 12:53, Friday 26 March 2021

Sent to Northamptonshire Highways less than a minute later. ref: 2635259.

Photo of this report zoom

Redact

About 3 months ago someone highlighted this hole and several other all the way down Membris Way-there was yellow markings put around them all-what a waste of time and money that was, as all the marking have all now washed away and the road has not been sorted?!

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 12:54, Friday 26 March 2021

  • Thank you for your enquiry the location has previously been inspected and a job raised to be undertaken within the next 26 weeks

    State changed to: In progress

    Posted by Northamptonshire Highways at 13:45, Friday 26 March 2021

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 13:46, Friday 26 March 2021

  • Fixed within the next 26 weeks?? Blimey I wish I worked in road repairs-one hole a day and job done-that’s 5 minutes work and then rest of the day sitting in a van laughing at the people paying them! It has already been over 12 weeks since this road was reported. Why was someone sent to Mark yellow marks rather than fix the issues?? The yellow markings have washed away-what a waste of money!! I guess we will need someone else to come out and re-Mark all the areas now??!! How do we get a discount on the tax we pay?

    Posted anonymously at 21:05, Friday 26 March 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 21:06, Friday 26 March 2021

  • State changed to: In progress

    Updated by Northamptonshire Highways at 17:50, Saturday 27 March 2021

  • Photo of this report zoom

    Redact

    This is now very dangerous to cyclists, 26 weeks is neglect!

    Posted anonymously at 18:23, Wednesday 26 May 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 18:24, Wednesday 26 May 2021

  • I note finally now in progress-I certainly hope that means the whole of Membris Way will be done-the same road that you spent money on sending someone to put yellow marking all the way down the road-FYI-the yellow marking have long disappeared-so please ensure the whole road is done while sending people out! After all we have already paid someone for nothing marking yellow lines!

    State changed to: Investigating

    Posted anonymously at 20:47, Wednesday 26 May 2021

  • State changed to: In progress

    Updated by Northamptonshire Highways at 06:50, Thursday 27 May 2021

  • Hole now showing substrate and vehicles swerving

    Posted anonymously at 16:49, Monday 31 May 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 16:49, Monday 31 May 2021

  • State changed to: In progress

    Updated by Northamptonshire Highways at 17:20, Monday 31 May 2021

  • Thank you for reporting a fault on the highway, the highways team have now resolved the issue.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 12:00, Tuesday

This report is now closed to updates. You can make a new report in the same location.