Back to all reports

Many large pirholes

Reported via mobile in the Potholes / Highway Condition category anonymously at 08:54, Monday 24 May 2021

Sent to Northamptonshire Highways less than a minute later. ref: 2744904.

Potholes all been here for a few months. They re appear every few months . Urgently need reapairing again. (Which is being filled in by yourselves only to re appear). Please re surface that small bit if road.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 08:54, Monday 24 May 2021

  • Thank you for your enquiry and for bringing this matter to our attention. We understand that you have concerns about the condition of Hillside Road; specifically, that you feel there are potholes present that are risk to road users. We appreciate your concerns and have carried out an assessment of the issue and are pleased to confirm that the carriageway defects, that meet the specifications for remedial work that you have indicated in this location, has a repair scheduled to resolve them. This should be completed within five months’ time. Please be assured that you will receive an update once repairs are concluded.

    State changed to: In progress

    Posted by Northamptonshire Highways at 15:17, Monday 24 May 2021

  • Holes are right across the road making it impossible to pass without going into the potholes. Should make it easier to claim damage from the coucil though

    Posted anonymously at 09:24, Thursday 29 July 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 09:28, Thursday 29 July 2021

  • Thank you for your further comments. Unfortunately, due to the number of outstanding works orders, we cannot commit to bringing the works order forward in the programme. Whilst we appreciate and sympathise with your comments, the current timeframe we have is that work is to be completed within five months from the 24th of May. In some cases, we are able to attend before this prospective time; however, at this time, we have no further information other than the timeframe given above.

    State changed to: In progress

    Posted by Northamptonshire Highways at 15:13, Thursday 29 July 2021

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you