The whole street is full of pot holes

Reported via mobile in the Potholes / Highway Condition category anonymously at 17:29, Saturday 12 June 2021

Sent to Northamptonshire Highways less than a minute later. ref: 2787412.

The pot holes have been like this for more than 6 months reported repeatedly and cars have been damaged by them they are not marked up or if they have been they are now faded without being repaired.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 17:29, Saturday 12 June 2021

  • Thank you for your enquiry and for bringing this matter to our attention. We understand that you have concerns about the condition of Kingsley Road; specifically, that you feel that there are multiple potholes present creating a dangerous hazard for motorists and damage to vehicles. We appreciate your concerns and have carried out an assessment of the issue and are pleased to confirm that the carriageway defects, that meet the specifications for remedial work that you have indicated in this location, has a repair scheduled to resolve them. This should hopefully be completed within four months’ time. Please be assured that you will receive an update once repairs are concluded.

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:39, Tuesday 15 June 2021

  • As a resident living on Kingsley Road I’m appalled on the condition of the road, it’s full of potholes and uneven road in which cars are hitting their front bumper valance. We’ve had potholes filled in several times but they just keep reappearing. Ideally the whole road needs a new complete road surface.

    Posted anonymously at 08:45, Wednesday 7 July 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 08:45, Wednesday 7 July 2021

  • Thank you for your further comments. Unfortunately, due to the number of outstanding works orders, we cannot commit to bringing the works order forward in the programme. Whilst we appreciate and sympathise with your comments, the current timeframe we have is that work is to be completed within four months from the 15th of June. In some cases, we are able to attend before this prospective time; however, at this time, we have no further information other than the timeframe given above.

    State changed to: In progress

    Posted by Northamptonshire Highways at 15:09, Monday 12 July 2021

  • This report is under further investigation.

    State changed to: Under further investigation

    Posted by Northamptonshire Highways at 15:09, Monday 12 July 2021

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

or No personal details will be stored, and you will not receive updates about this report.

Your update

Tell us about you

Do you have a FixMyStreet password?