A number of drains blocked on Main Street
Reported via desktop in the Blocked/Damaged category anonymously at 09:39, Wed 4 August 2021
Sent to Northamptonshire Highways less than a minute later. ref: 2913191.
Many of the road drains between approximately opposite the Garage near Cross Lane to outside the Village Hall are blocked so that when there any heavier rain at all the road and pathway are flooded. This was the case on 30 July, following rainfall. Earlier in the year one of the houses has also been flooded due to ineffective drains (this was reported in January see ref 2485400). Another report has also been made about these blocked drains (ref 2510432), and action has, I think yet to be taken on these. The endemic drainage issues affecting Main Street and Cross Street have also been reported directly to North Northants Council via Aldwincle Parish Council and will be subject to follow up meetings and action.
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 09:40, Wed 4 August 2021
-
Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so.
State changed to: In progress
Posted by Northamptonshire Highways at 11:32, Thu 5 August 2021
-
Road markings at the junction lowick road and main Street aldwincle traffic just carry on and don't look if any vehicle is on the road five near misses in the last week
Posted anonymously at 15:59, Mon 25 October 2021
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 15:59, Mon 25 October 2021
-
Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so. Update 1.11.21. Thank you for your enquiry. We have raised a works order to repair the road marking defects that you have reported. These works will be undertaken within the next 5 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out further assessment, attaching a photograph if possible and safe to do so.
State changed to: Closed
Posted by Northamptonshire Highways at 09:46, Mon 1 November 2021