Concrete pathway has deteriorated and is becoming a trip hazard

Reported via desktop in the Slabs - Uneven / Damaged / Cracked category anonymously at 14:14, Tuesday 21 September 2021

Sent to Northamptonshire Highways less than a minute later. ref: 3015838.

The concrete outside number 8 Simpson Avenue on the footpath is deteriorating and could cause a trip hazard. There is also a CATV wire exposed and the black outer cable is being worn away and the silver is beginning to show due to exposure.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 14:14, Tuesday 21 September 2021

  • State changed to: In progress

    Updated by Northamptonshire Highways at 11:19, Tuesday 28 September 2021

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:19, Tuesday 28 September 2021

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 11:20, Tuesday 28 September 2021

  • Thank you for your enquiry and for bringing this matter to our attention. We understand you have concerns about the condition of the footpath on Simpson Avenue. Following our inspector’s visit, we are pleased to confirm that the footway defects, that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:25, Tuesday 28 September 2021

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:05, Friday 8 October 2021

  • Thank you for reporting a fault on the highway, the highways team have now resolved the issue.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 07:35, Tuesday 26 October 2021

This report is now closed to updates. You can make a new report in the same location.