Blocked drains causing flooding in underpass
Reported via desktop in the Obstruction (Not Vegetation) category anonymously at 17:40, Sat 16 October 2021
Sent to Northamptonshire Highways less than a minute later. ref: 3066382.
The drains (4 off) at either end of the underpass at the end of Ladybridge Drive under Mere Way are blocked by earth and vegetation. When the pictures were taken there had been no rain for over a week. In moderate rain the underpass will flood. The size of the drain appears to be inadequate and there is no surrounding brickwork to stop the bank collapsing and washing down to block the drains.
Updates
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 17:41, Sat 16 October 2021
-
State changed to: In progress
Updated by Northamptonshire Highways at 08:50, Fri 22 October 2021
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 08:52, Fri 22 October 2021
-
Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.
State changed to: Investigating
Posted by Northamptonshire Highways at 09:37, Fri 22 October 2021
-
Thank you for your enquiry and for bringing this matter to our attention. We understand that you have concerns about the condition of the drains on Danes Camp Way. We note with regret, that you feel they are blocked and may pose a flooding risk. We are pleased to confirm that the problem you have indicated in this location, has a work order to investigate, clean and test the gully. This should hopefully be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.
State changed to: In progress
Posted by Northamptonshire Highways at 09:42, Fri 22 October 2021
-
Thank you for reporting a fault on the highway, the highways team have now resolved the issue.
State changed to: Fixed
Posted by Northamptonshire Highways at 13:55, Tue 2 November 2021
-
The drains are still blocked. The bank has been cut back but it will collapse again into the drain. It needs a brick/concrete surround to prevent the erosion. A competent surveyor should asses the problem and determine a schedule of work. I have reported the problem again.
State changed to: Open
Posted anonymously at 18:09, Sat 13 November 2021
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 18:10, Sat 13 November 2021
-
The drains are still blocked. The bank has been cut back but it will collapse again into the drain. It needs a brick/concrete surround to prevent the erosion. A competent surveyor should asses the problem and determine a schedule of work. I have reported the problem again.
State changed to: Open
Posted anonymously at 20:19, Sat 13 November 2021
Still open, via questionnaire -
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 08:24, Mon 15 November 2021
-
Thank you for your further comments. Whilst we understand your frustration, we can confirm that the gullies are designed to a specific specification and we are only to maintain the gullies at this area. Should any revision be recommended or advanced in the future, we would endeavour to make these changes here.
State changed to: In progress
Posted by Northamptonshire Highways at 09:19, Mon 15 November 2021
-
Still open, via questionnaire, 20:45, Sat 11 December 2021
-
This report is under further investigation.
State changed to: Under further investigation
Posted by Northamptonshire Highways at 16:00, Wed 19 January 2022
-
State changed to: In progress
Updated by Northamptonshire Highways at 11:30, Thu 20 January 2022
-
This report has been assessed and a job for repair has been raised.
State changed to: Action scheduled
Posted by Northamptonshire Highways at 11:32, Thu 20 January 2022
-
Thank you for your further comments, and your continued patience on this matter. We have passed your comments on to the drainage team, who have confirmed that the drains will be cleansed within the next month. Please be assured you will be updated once the repair is complete.
State changed to: In progress
Posted by Northamptonshire Highways at 11:59, Thu 20 January 2022
-
As part of a system review we have noted that this report has remained open and we have now closed the report to future updates.
If for any reason you believe that the report should not have been closed please raise a new report.
Please provide the old reference number and an explanation as to why you believe the report should not have been closed so we can investigate this further.
State changed to: Closed
Posted by Northamptonshire Highways at 13:54, Tue 21 March 2023
This report is now closed to updates from the public. You can make a new report in the same location.