Over hanging shrubbery & thorns

Reported via mobile in the Restricted Visibility / Overgrown / Overhanging category anonymously at 09:29, Thu 4 November 2021

Sent to Northamptonshire Highways less than a minute later. ref: 3103735.

The path is unusable for pedestrians, cyclists or e-scooters as the overgrown and over hanging vegetation prevents this. Its poorly lit so you don't see the hanging thorns before it's too late at night.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 09:30, Thu 4 November 2021

  • Thank you for your enquiry. This will be investigated and an update will be provided within the next 10 working days,

    Posted by Northamptonshire Highways at 10:42, Tue 9 November 2021

  • Thank you for your enquiry. A letter has been sent to the relevant landowner requesting that the overhanging vegetation is cut back. A revisit will be carried out 14 days after the receipt of the letter.

    Posted by Northamptonshire Highways at 12:58, Fri 12 November 2021

  • 14/12 Passed to Regulation Team for further enforcement. Letter to owner to be sent week commencing 13/12 and final inspection to be carried out week commencing 27/12

    Posted by Northamptonshire Highways at 12:38, Tue 14 December 2021

  • 17/01 A further site visit has been carried out and the vegetation has not been cut back enough. Another letter has been sent and a further site visit will be carried out week commencing 07/02

    Posted by Northamptonshire Highways at 16:35, Monday 17 January 2022

  • 17/02 An enforcement letter will be sent week commencing 25/02 and a further site visit will be carried out week commencing 14/03

    Posted by Northamptonshire Highways at 11:32, Thursday 17 February 2022

  • 17/02 An enforcement letter will be sent week commencing 21/02 and a further site visit will be carried out week commencing 14/03

    Posted by Northamptonshire Highways at 12:36, Thursday 17 February 2022

  • 15/03 A further site visit has been carried out and the vegetation has been cut back

    State changed to: No further action

    Posted by Northamptonshire Highways at 14:29, Tuesday 15 March 2022

This report is now closed to updates. You can make a new report in the same location.