Back to all reports

Cracked & loose slab + Equalities Act 2010

Reported via desktop in the Slabs - Uneven / Damaged / Cracked category by Peter Drabble at 11:18, Mon 22 November 2021

Sent to Northamptonshire Highways less than a minute later. ref: 3136950.

Ther are some loose paving slabs and one cracked. As Churchwarden to the Church I am also acutely aware of non-compliance with regard to access to the church. The Church has some issues to address (eg path handrail etc however I understand the steps are within Council demise and a discussion is required with regard to ramp or some other addressable requirement to ensure legal requirements are met. Any help in this matter would be very much appreciated

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:19, Mon 22 November 2021

  • State changed to: In progress

    Updated by Northamptonshire Highways at 09:20, Wed 24 November 2021

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:22, Wed 24 November 2021

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 09:23, Wed 24 November 2021

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:25, Wed 24 November 2021

  • Thank you for your enquiry and for bringing this matter to our attention. We understand that you have concerns about the condition of the footpath in this area; specifically, that you feel there are cracked slabs present. We are pleased to confirm that the footway defects, that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within a month’s time. Please be assured that you will receive an update once repairs are concluded. For transport and highway updates, please follow us on Twitter @nnhighways. You can also see roadworks, ours and utilities, view diversions and plan your journeys by visiting https://one.network/

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:32, Wed 24 November 2021

  • Thank you for reporting a fault on the highway, the highways team have now resolved the issue.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 08:55, Thu 2 December 2021

This report is now closed to updates. You can make a new report in the same location.