Back to all reports

Builders have Damaged and Marked the Road and Footpath's on Gloucester Crescent

Reported via desktop in the Potholes / Highway Condition category anonymously at 11:24, Fri 26 November 2021

Sent to Northamptonshire Highways less than a minute later. ref: 3144977.

Builders have been in the area and they have left the highway in poor condition. They have been working on Gloucester Crescent, top end by number 61 and surrounding houses, and they have left marks on the road and footpath, they have also caused damage leaving the highway in poor condition. The damage has been caused by a digger. The builders have also been working on Gloucester Avenue (around the corner) and have caused the same damage and marks on the road.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 11:24, Fri 26 November 2021

  • 10/12 A site visit will take place within the next 10 working days and then you will receive an update

    Posted by Northamptonshire Highways at 16:38, Fri 10 December 2021

  • 21/12 A site visit has taken place and no damage was seen to the public highway in the areas given. This report will now be closed

    State changed to: No further action

    Posted by Northamptonshire Highways at 16:44, Tue 21 December 2021

This report is now closed to updates. You can make a new report in the same location.