Access bollards at the end of Hoylake are missing and damaged

Reported via desktop in the Safety Bollard - Damaged/Missing category anonymously at 13:33, Wednesday 8 June 2022

Sent to Northamptonshire Highways less than a minute later. ref: 3580877.

Access bollards at the end of Hoylake are missing and damaged. Customer advised that suspected travellers have been assessing whether vehicles could pass through the gap as it is access to a field with a stream. There are enough damaged or missing for a truck to get through

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. We will use the information you have provided to assess and prioritise this fault in accordance with our published response times for fault reports.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 13:33, Wednesday 8 June 2022

  • As you can see, missing posts leave a gap wide enough for trucks to get through. Loads of other posts are perished and easily removed. Saw some travellers assessing the area this morning, they were kicking and twisting the remaining posts to see which could be removed. The field is at the bottom of a residential area but would be prime location for travellers, with a large plot for trailers and a steam running through. Really hoping you could fix this asap to prevent travellers setting up camp there.

    Posted anonymously at 13:52, Wednesday 8 June 2022

  • State changed to: In progress

    Updated by Northamptonshire Highways at 13:30, Thursday 9 June 2022

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 13:32, Thursday 9 June 2022

  • Thank you for your enquiry. We have raised a works order to repair the defects that you have reported. These works will be undertaken within the next 6 months. On most occasions we are repairing defects of this nature sooner than this target date, however please do not hesitate to contact us should the defects worsen so that our team can carry out a further assessment, attaching a photograph if possible and safe to do so.

    State changed to: In progress

    Posted by Northamptonshire Highways at 13:57, Thursday 9 June 2022

  • Thank you for reporting a fault on the highway, the highways team have now resolved the issue.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 07:40, Thursday 14 July 2022

This report is now closed to updates. You can make a new report in the same location.