Faded Road Markings

Reported via desktop in the Road Markings - Worn/Faded category anonymously at 16:10, Wed 10 August 2022

Sent to Northamptonshire Highways less than a minute later. ref: 3744958.

Please can the road markings in the parking bays be repainted.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 16:10, Wed 10 August 2022

  • State changed to: In progress

    Updated by Northamptonshire Highways at 08:50, Thu 11 August 2022

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 08:52, Thu 11 August 2022

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 08:52, Thu 11 August 2022

  • This report has been assessed and a job for repair has been raised.

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 08:55, Thu 11 August 2022

  • Thank you for your enquiry and for bringing this matter to our attention. We understand that you have concerns about the condition of the road markings in this section of road. We are pleased to confirm that the problem you have indicated in this location, has work scheduled to resolve it. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:24, Thu 11 August 2022

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 15:54, Thu 10 November 2022

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:54, Wed 16 November 2022

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 07:13, Wednesday 4 January 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:19, Friday 6 January 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 10:56, Tuesday 14 February 2023