Slabs are loose and dropped

Reported via desktop in the Slabs - Uneven / Damaged / Cracked category anonymously at 09:31, Tuesday 20 September 2022

Sent to Northamptonshire Highways less than a minute later. ref: 3835057.

Potential trip hazard, the slabs have dropped all along the front of Gilders, causing rainwater to drain into the shop's cellar. Some slabs are mobile. This has been an issue for more than 12 months but is getting worse, there are now slabs that rock when you stand on them and the slabs in front of the window have subsided by 10cms.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 09:31, Tuesday 20 September 2022

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry and for bringing this matter to our attention, regarding the footpath adjacent to Wellingborough Road. We are pleased to confirm that the footway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within a month's time. Please be assured that you will receive an update once repairs are concluded.

    Posted by Northamptonshire Highways at 10:15, Wednesday 21 September 2022

  • Investigation: Completed (Defect Found), Defect Repair: Not Started

    Posted by Northamptonshire Highways at 11:29, Thursday 22 September 2022

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 11:34, Thursday 22 September 2022

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:06, Friday 23 September 2022

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 09:40, Monday 26 September 2022

This report is now closed to updates. You can make a new report in the same location.