Unfinished work

Reported via Android in the Slabs - Uneven / Damaged / Cracked category anonymously at 17:17, Mon 10 October 2022

Sent to Northamptonshire Highways less than a minute later. ref: 3880642.

Hi they've repaired the entrance to the flats but they haven't repaired the footpath which I sent you a photo of. My neighbour and I are both disabled and have tripped on the path and is very uncomfortable on our scooters and we both have back problems. Please can you look into this Many thanks Karen Bagnall 75 Hazelwood Road Corby NN17 1HS

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 17:17, Mon 10 October 2022

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Firstly, we are sorry to hear you have tripped in this area. Regarding this section of Dovesale Road, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 11:30, Wed 12 October 2022

  • Still open, via questionnaire, 18:02, Mon 7 November 2022

  • The footpath has still not been fixed which I reported on 13th October 2022. The yellow spray marks which they put by the repair have now disappeared. I tripped over again on the uneven pavement 3 wks ago and hurt my knee . Please can you advise when it's going to be repaired as it's very dangerous

    Posted anonymously at 10:13, Wednesday 8 February 2023

  • The above footpath has still not been repaired and is now 6 months later. The yellow spray which was highlighted which part to be fixed has now been washed away. I have fell over on this footpath since

    Posted anonymously at 17:07, Thursday 13 April 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:39, Thursday 14 September 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:04, Friday 15 September 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 10:19, Friday 15 September 2023

This report is now closed to updates. You can make a new report in the same location.