Fallen sign at the entrance to the Bridleway
Reported via desktop in the Damaged / Missing / Facing Wrong Way category by Kerry Stevens at 12:05, Tue 1 November 2022
Sent to Northamptonshire Highways less than a minute later. ref: 3929495.
This was knocked by the company who were replacing the electricity pylons in the field of my property. It was fixed but clearly it was cracked as I think the wind last night has brought it down.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 12:05, Tue 1 November 2022
-
Hi discussed with the gentleman who picked up the fallen sign. The sign is way to low down he said. The bottom sign of the 3 should be removed and put on a single pole. he suggested the 2 top signs need to g on a longer pole and can go back where the pole initianally was. The new pole with the bridge sign on it he mentioned should be put a bit further back on Brdige road as I already have ab electricity pole next to the house and the pole with the 2 signs on it. Only recently moved here and driving out was a real issue. As I work from 8 till 5 it is rather dark to take a picture atm
Posted anonymously at 17:50, Fri 4 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding the condition of sign adjacent to Bridge road, we are pleased to confirm this matter has a repair scheduled to resolve it and should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 10:53, Mon 7 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 09:15, Tue 20 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 11:34, Tue 20 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 12:53, Tue 20 June 2023
This report is now closed to updates from the public. You can make a new report in the same location.