Reported via desktop in the Potholes / Highway Condition category anonymously at 16:27, Fri 18 November 2022
Sent to Northamptonshire Highways less than a minute later. ref: 3975433.
Recurring pothole on n/s carriageway heading out of St James Mill Road, first occurred last year, is back and deep.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 16:27, Fri 18 November 2022
-
A pothole of some depth outside 35-37 St James Mill Road going out of the said Road. I came from work, 45-47 of said Road, driving home, the pothole full of water as it's been raining all day. As it was around 17.45pm it was dark, I went into the pothole which I was unable to see as water had filled the pothole and was slightly flooded over the road. On arriving home tyre flat/ruined had the AA out to change it. Pothole is an issue which had it not been there I wouldn't of had this incident.
Posted anonymously at 20:50, Mon 21 November 2022
-
This pothole is seriously dangerous and needs immediate attention. It cannot be avoided without going onto the other side of the road, and cannot be seen easily in the dark and rain when it is full of water. It is around 130mm deep. At 16:45 on 22/11/22 it ripped a tyre off the rim. The photo I have uploaded shows a 30cm ruler half submerged in the pot hole...
Posted anonymously at 08:10, Tue 22 November 2022
-
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:06, Tue 22 November 2022
-
Investigation: Not Started (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 10:47, Tue 22 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing - Regarding this section of St. James Mill Road, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within a weeks’ time. Please be assured that you will receive an update once repairs are concluded.
Posted by Northamptonshire Highways at 11:45, Thu 24 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 09:44, Wed 30 November 2022
This report is now closed to updates from the public. You can make a new report in the same location.