Large pothole.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 16:21, Mon 21 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Welton Lane, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 09:12, Tue 22 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 11:55, Tue 22 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 08:49, Tue 29 November 2022
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 09:17, Tue 29 November 2022