Fixed
Hole next to ironware in road.
Reported via desktop in the Potholes / Highway Condition category anonymously at 16:33, Fri 2 December 2022
Sent to Northamptonshire Highways less than a minute later. ref: 4010192.
This pothole has been getting increasingly larger/deeper for a few weeks following cracking in the road surface next to ironware. It is very difficult to avoid driving through it due to vehicles being parked on both sides of the road. At night time it is impossible to avoid it unless you are aware of it.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 16:34, Fri 2 December 2022
-
Questionnaire filled in by problem reporter; State changed to: Fixed, 11:22, Monday 2 January 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Kingsley Avenue, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 12:19, Friday 21 April 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 13:13, Thursday 14 September 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 07:01, Monday 18 September 2023
This report is now closed to updates. You can make a new report in the same location.