You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Start new report here Reposition report here
Back to all reports

Subsided

Reported via desktop in the Potholes / Highway Condition category anonymously at 07:29, Thursday 5 January 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4088594.

Subsidence to road as you drive towards Thrapston

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 07:29, Thursday 5 January 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of the A605, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 14:23, Thursday 12 January 2023

  • I reported this in February of 2022 and the council response then was that it would be fixed within 6 months but it is still the same a year later. I won't be holding my breath. However who will take responsibility when someone is injured or worse when a truck tips over because of this dangerous situation?

    Posted anonymously at 16:43, Thursday 19 January 2023

  • It is now mid March 2023. This was reported in February 2022. That is over a year. So the 6 month promise is laughable.

    Perhaps this is one for the press, with a video of course.

    Posted anonymously at 18:47, Tuesday 14 March 2023

  • Hmmm 13 weeks eh? It's now been 21 weeks since the second reporting. Great work Northamptonshire Highways have a piece of cake you deserve it.

    Posted anonymously at 11:58, Friday 9 June 2023

  • Still not fixed.

    Posted anonymously at 16:08, Friday 16 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 08:13, Friday 7 July 2023

  • This item has not been rectified since May 2021. report 2716999 10 May 2021 report 4088594 5 Jan 2023 report 4346628 Jan 2023 report 4316657 March 2023 report 4763401

    There has been a partial temporary fix. There have been repeated promises of a full repair within six months, pushing back the date every time. Last one was to fix by 13 July 2023. This issue has been there since the start of 2021 - over TWO years ago. Today is 12th July.

    Posted anonymously at 10:42, Wednesday 12 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:04, Thursday 13 July 2023

  • "In progress" No it isn't

    Posted anonymously at 13:59, Thursday 20 July 2023

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 13:59, Thursday 20 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing - An inspector has been sent to the area and the problem will be resolved on/by July 26th 2023. You will receive further information when this job is completed.

    Posted by Northamptonshire Highways at 09:52, Tuesday 25 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 15:08, Wednesday 26 July 2023

This report is now closed to updates. You can make a new report in the same location.