A large number of potholes along the whole road. It's like driving along a chicane trying to miss them.
Reported via desktop in the Potholes / Highway Condition category anonymously at 17:42, Tuesday 24 January 2023
Sent to Northamptonshire Highways less than a minute later. ref: 4162686.
The potholes are now worse than ever along the whole street. I am a car driver and have to weave along the road where this is possible to avoid destroying my tyres. If I rode a motorbike I would have serious concerns for my personal welfare. The holes have been present for months and are now getting progressively worse. When is something going to be actioned to sort this out.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 17:42, Tuesday 24 January 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Carriage Drive, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 13:18, Tuesday 31 January 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 12:59, Friday 26 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 09:13, Tuesday 30 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 15:29, Tuesday 30 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 15:03, Wednesday 31 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 15:50, Thursday 1 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 05:45, Friday 2 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 14:14, Monday 19 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 15:59, Tuesday 20 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 07:41, Thursday 22 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 11:01, Thursday 22 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 11:41, Friday 7 July 2023
This report is now closed to updates. You can make a new report in the same location.