Road breaking away, deeper than 50mm
Reported via mobile in the Potholes / Highway Condition category anonymously at 10:39, Wednesday 1 February 2023
Sent to Northamptonshire Highways less than a minute later. ref: 4192199.
Pothole is at the Junction with the A5, the pothole is causing vehicles to move and stop to the centre of the Junction. Which is then not allowing vehicles travelling North Bound on the A5 to turn left into the Junction, causing them to have to stop on a 50mph road and wait for the vehicle to exit the Junction.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 10:39, Wednesday 1 February 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Deanshanger Road, we are pleased to confirm that the carriageway defects that meet the specifications for remedial work, have a repair scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 15:39, Monday 6 February 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 19:56, Monday 27 February 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 12:48, Thursday 2 March 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 13:28, Thursday 2 March 2023
This report is now closed to updates. You can make a new report in the same location.