Mini island give way markings faded,junction of arthur street and northampton road,all markings on roundabout faded

Reported via mobile in the Road Markings - Worn/Faded category anonymously at 18:52, Thursday 2 March 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4277806.

Faded road markings on mini roundabout ,junction of arthur street and northampton road.location is wellingborough

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 18:53, Thursday 2 March 2023

  • Investigation: Ongoing - We can confirm that this issue will be investigated within a weeks' time and we will update you accordingly.

    Posted by Northamptonshire Highways at 15:56, Thursday 9 March 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding the condition of road markings on this section of Northampton Road we are pleased to confirm that a works order has been raised, to be carried out within the next 28 days. Please be assured that you will receive an update once repairs are concluded.

    Posted by Northamptonshire Highways at 10:50, Monday 17 April 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 08:51, Tuesday 9 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 14:32, Thursday 25 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 01:53, Wednesday 21 June 2023

This report is now closed to updates. You can make a new report in the same location.