Storm Drain Breaking Up Again.

Reported via desktop in the Blocked/Damaged category anonymously at 14:40, Tuesday 14 March 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4312460.

Sorry but the recently repaired drain next to the bus stop on Main Road, Wilby NN8 2UB (geologist.incomes.painted) is breaking up again. The steel grid covering the drain is subjected to a pounding with loud noises. Grateful if you could inspect. Thanks.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 14:40, Tuesday 14 March 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding the condition of the drain adjacent to Main Road, we can confirm that a works order has been raised. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.

    Posted by Northamptonshire Highways at 13:13, Tuesday 21 March 2023

  • Awaiting action by the contractor.

    Posted anonymously at 15:39, Tuesday 11 April 2023
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 13:47, Thursday 13 April 2023

  • Awaiting repair action.

    Posted anonymously at 15:16, Thursday 13 April 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 13:30, Monday 17 April 2023

  • Repaired, thank you.

    Posted anonymously at 14:37, Monday 17 April 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 15:17, Monday 17 April 2023

  • Whilst grateful for the repair it doesn't look permanent. There are signs of cracking surrounding the drain and maybe even some subsidence. I feel it may take another, more substantial repair to complete this problem. Thanks

    State changed to: Open

    Posted anonymously at 12:20, Wednesday 10 May 2023
    Still open, via questionnaire

  • Whilst the repair is appreciated, quite a speedy job, a short while after completion, cracks started to reappear. I get the impression a more invasive repair is necessary. I will be reporting the situation here, should it deteriorate further.

    Posted anonymously at 15:30, Wednesday 7 June 2023
    Still open, via questionnaire

  • Still crumbling

    Posted anonymously at 14:29, Thursday 6 July 2023
    Still open, via questionnaire

  • Part of the structure of the drain is now collapsing into the drain below, as can clearly be seen from the attached photograph. I believe it is only a matter of time before it falls in on itself to deepen and enlarge the hole in the road, right next to the bus stop. Thanks.

    Posted anonymously at 15:20, Saturday 15 July 2023

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Fixed

    Posted by Northamptonshire Highways at 15:20, Saturday 15 July 2023

  • Investigation: Completed (Scheduled Maintenance), Defect Repair: Completed (Work Completed) - We have raised a further ticket to reset the gully, which would be completed within 28 days.

    Posted by Northamptonshire Highways at 09:44, Wednesday 19 July 2023

This report is now closed to updates. You can make a new report in the same location.