Large pot hole

Reported via Android in the Pothole / Failed Reinstatement category anonymously at 10:25, Saturday 25 March 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4356885.

A large pot hole has formed on the left hand side as you drive in this is dangerous to bikers

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 10:25, Saturday 25 March 2023

  • Investigation: Ongoing - Thank you for your enquiry. We have undertaken an initial assessment of your report and we will investigate this matter and respond within 7 days.

    Posted by Northamptonshire Highways at 15:37, Friday 31 March 2023

  • Still open, via questionnaire, 11:48, Saturday 22 April 2023

  • Questionnaire filled in by problem reporter

    State changed to: Fixed

    Posted anonymously at 12:02, Saturday 20 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Hawthorn Road, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 14:14, Thursday 25 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 12:52, Tuesday 13 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:46, Wednesday 14 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 10:15, Wednesday 14 June 2023

This report is now closed to updates. You can make a new report in the same location.