Fixed
Many potholes
Reported via mobile in the Potholes / Highway Condition category anonymously at 18:24, Monday 10 April 2023
Sent to Northamptonshire Highways less than a minute later. ref: 4421495.
Numerous deep potholes going into Little Everdon
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 18:24, Monday 10 April 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your report. We have raised a works ticket and this will be addressed within the next 6 months.
We make our decision to repair a road based on a number of factors. We need to look at the location, inspections and public reports, the road condition and the best way to spend the funds we have available to us, with our priority being on safety for all road users. This does mean that some roads will take priority over others and we are not able to fix every report that comes in to us immediately.
For more information about our services and our criteria for repairing defects, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by Northamptonshire Highways at 13:13, Thursday 13 April 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 10:15, Wednesday 17 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 08:58, Friday 19 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 15:55, Friday 19 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 06:53, Monday 22 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled (Work Completed)
State changed to: Action scheduled
Posted by Northamptonshire Highways at 07:47, Thursday 1 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)
State changed to: In progress
Posted by Northamptonshire Highways at 08:28, Monday 5 June 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 15:31, Monday 5 June 2023
This report is now closed to updates. You can make a new report in the same location.