Fixed
Multiple potholes
Reported via mobile in the Potholes / Highway Condition category anonymously at 11:14, Tuesday 2 May 2023
Sent to Northamptonshire Highways less than a minute later. ref: 4507610.
There are a number of potholes right on, and on the approach to the bridge on both sides. Please carry out meaningful repairs as there are signs of half hearted repairs right next to the current potholes
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 11:14, Tuesday 2 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Medbourne Road, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.
Posted by Northamptonshire Highways at 09:46, Thursday 4 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 08:32, Tuesday 30 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 10:57, Wednesday 31 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 11:19, Monday 14 August 2023
This report is now closed to updates. You can make a new report in the same location.