Fixed
Pothole in road outside 3 Plumtree Avenue Wellingborough
Reported via desktop in the Potholes / Highway Condition category anonymously at 15:39, Friday 19 May 2023
Sent to Northamptonshire Highways less than a minute later. ref: 4574492.
The ‘fillet’ around one side of a manhole cover in the road has broken into several largish pieces leaving a hole.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by Northamptonshire Highways at 15:39, Friday 19 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Plumtree Avenue, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 08:15, Friday 26 May 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by Northamptonshire Highways at 08:27, Friday 30 June 2023
-
This defect has still not been fixed yet but a pothole less than 100m away was repaired. Surely the two defects could have been dealt with at the same time to save money by only having one visit.
Posted anonymously at 09:35, Monday 7 August 2023
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by Northamptonshire Highways at 09:35, Monday 7 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - Regarding this section of Plumtree Avenue, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.
Posted by Northamptonshire Highways at 15:47, Tuesday 8 August 2023
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by Northamptonshire Highways at 10:27, Monday 25 September 2023
-
Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)
State changed to: Fixed
Posted by Northamptonshire Highways at 10:55, Monday 25 September 2023
This report is now closed to updates. You can make a new report in the same location.