Several potholes in Avenue

Reported via mobile in the Potholes / Highway Condition category anonymously at 07:46, Wednesday 24 May 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4589333.

These pot holes have been here for weeks and getting bigger

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 07:46, Wednesday 24 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding this section of Browning Avenue, we can confirm that the carriageway defects that meet the investigatory level for repairs, have work scheduled to resolve them. This should be completed within six months’ time. Please be assured that you will receive an update once repairs are concluded. We usually find these defects are tended to within 13 weeks.

    Posted by Northamptonshire Highways at 09:41, Wednesday 31 May 2023

  • Good morning The photos attached are off the injury’s that my daughter sustained after falling off her bike due to the potholes in Browning avenue. I am very upset to learn that the potholes were first reported in May and no repairs have been made. I believe that my daughter’s injuries could have been avoided. I look forward to your response.

    Posted anonymously at 08:27, Tuesday 11 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 10:35, Thursday 13 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:31, Friday 14 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 09:05, Friday 14 July 2023

This report is now closed to updates. You can make a new report in the same location.