Very poor repair carried out yesterday

Reported via mobile in the Damaged/Loose category anonymously at 20:05, Thu 25 May 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4597544.

Three guys came yesterday and carried out a very poor job, they refitted the kerbs higher than they were knowing this is a dropped kerb driveway and should be flush with the road and cobbles and they left the dangerous dip in the road which means that the kerb will come off again and public will continue to fall over. I would have been able to conduct a better job than those three guys did - it’s a complete waste of taxpayer money and will now cause tyre and suspension damage and public to fall - this is a conservation area where council don’t allow sloppy work outside by residents but allow this kind of poor work and appearance to be left by their own work people - I’m sorry but it’s embarrassing and needs to be rectified.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 20:05, Thu 25 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 28 days
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 09:33, Tue 30 May 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 10:42, Tue 13 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:08, Mon 19 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 12:16, Mon 19 June 2023

This report is now closed to updates from the public. You can make a new report in the same location.