Low tree vegetation makes exit from Green Dragon and John White is dangerous

Reported via desktop in the Restricted Visibility category anonymously at 17:39, Wednesday 31 May 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4616456.

These trees grow every season and need annual attention

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 17:39, Wednesday 31 May 2023

  • Investigation: Completed (Reported to a third party) - We are currently looking into removing the basal growth from the trees, we will update you when we know more
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    State changed to: not the council's responsibility

    Posted by Northamptonshire Highways at 14:50, Thursday 1 June 2023

  • Investigation: Ongoing (Reported to a third party) - We are currently looking into removing the basal growth from the trees, we will update you when we know more
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    State changed to: Investigating

    Posted by Northamptonshire Highways at 09:15, Monday 5 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding the vegetation, we can confirm that a works order has been raised to cut back the basal growth. This should be completed within a months’ time. Please be assured that you will receive an update once repairs are concluded.

    Posted by Northamptonshire Highways at 13:25, Friday 16 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 17:36, Tuesday 20 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 12:13, Wednesday 21 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 17:54, Wednesday 21 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing (Work Completed)

    State changed to: In progress

    Posted by Northamptonshire Highways at 13:00, Thursday 29 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 13:29, Friday 30 June 2023

This report is now closed to updates. You can make a new report in the same location.