Pavement collapsed outside 27 Glenfield Drive. Is not passable by wheelchairs / prams

Reported via desktop in the Verges - Damaged by Vehicles category anonymously at 10:53, Thursday 1 June 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4618560.

Delivery vehicle parked on the pavement on 25th May 2023 and sank into it.

The issue was reported to the company who contracted the haulier to make the delivery, their reply was:

I have had the following response from the haulage company.

"I have checked this with my Director and unfortunately, this isn’t something we would cover – this would be a council issue.

There is no way of knowing if this path was like this prior to the delivery made by the haulier.

I think the next best step to take with this is to report the issue to the local council with reference to the company that delivered".

Details of the delivery company and contractor are available (see No29) if needed.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 10:54, Thursday 1 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Regarding the condition of the footpath adjacent to Glenfield Drive, we are pleased to confirm that a works order has been raised. This should be completed within a weeks’ time. Please be assured that you will receive an update once repairs are concluded.

    Posted by Northamptonshire Highways at 11:32, Wednesday 7 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 13:04, Thursday 8 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 09:17, Saturday 10 June 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 09:35, Saturday 10 June 2023