The road has severe potholes in at least 3 pull in areas

Reported via desktop in the Potholes / Highway Condition category anonymously at 12:06, Thursday 13 July 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4782811.

This is a single track road with passing places which have very large holes in them and need urgent repairs

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 12:06, Thursday 13 July 2023

  • Investigation: Ongoing (Highways to Monitor, Routine Inspection Programme) - The area has been inspected and does not meet the criteria for repair, however, it will be continuously monitored. For further information on our pothole classifications go to https://www.westnorthants.gov.uk/ roads-and-paths-maintenance/ report-potholes-or-highway-problem
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by Northamptonshire Highways at 09:17, Monday 24 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.

    Posted by Northamptonshire Highways at 15:09, Tuesday 3 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 09:27, Wednesday 4 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 11:00, Monday 9 October 2023

  • Investigation: Completed (Defect Found), Defect Repair: Completed (Work Completed)

    State changed to: Fixed

    Posted by Northamptonshire Highways at 11:27, Tuesday 10 October 2023

This report is now closed to updates. You can make a new report in the same location.