Road surface condition very poor

Reported via desktop in the Potholes / Highway Condition category anonymously at 09:53, Sat 29 July 2023

Sent to Northamptonshire Highways less than a minute later. ref: 4837640.

The WHOLE of Latham Road needs to be inspected.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by Northamptonshire Highways at 09:53, Sat 29 July 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 12:56, Tue 1 August 2023

  • The whole of Latham rd , Oundle and St Peter’s rd are full of so many pot holes you can’t count them damaging cars as we drop in them , there are so many especially as this is has been the only route round the water works that has been going on for months , need fixing asap .

    Posted anonymously at 08:43, Fri 15 December 2023

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 08:43, Fri 15 December 2023

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - The area has been inspected and work has been scheduled to be carried out within the next 26 weeks. You will receive further information when this job is completed.
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 09:07, Tue 19 December 2023

  • Potholes still here, are they being fixed at same time as St. Peters Road?

    Posted anonymously at 14:10, Thursday 11 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 14:10, Thursday 11 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We have inspected the area and can confirm this will be repaired within 26 weeks, depending on weather conditions, we hope to be carrying out the repairs by January 30th 2024
    For more information about our services, please visit https://www.northnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @nnchighways

    Posted by Northamptonshire Highways at 13:19, Monday 22 January 2024

  • 26 weeks is unacceptable, but also says by 30th January 2024, which is it please

    Posted anonymously at 16:14, Monday 22 January 2024

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by Northamptonshire Highways at 16:15, Monday 22 January 2024

  • Lots of roads in Oundle need inspection and fixing, especially those getting more traffic because of other main road closures

    Posted anonymously at 09:25, Tuesday 23 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - We have inspected the area and can confirm this will be repaired within 26 weeks, depending on weather conditions, we hope to be carrying out the repairs by January 30th 2024

    Posted by Northamptonshire Highways at 11:33, Wednesday 24 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by Northamptonshire Highways at 11:49, Friday 26 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by Northamptonshire Highways at 08:28, Monday 29 January 2024

  • Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.

    Posted by Northamptonshire Highways at 09:06, Monday 29 January 2024

Provide an update